A project scheduler is modeling a situation where Activity B cannot start until 5 days after Activity A starts. Which type of dependency relationship best represents this?
-
A
Finish-to-Start with 5-day lag
-
B
Start-to-Start with 5-day lag
-
C
Finish-to-Finish with 5-day lead
-
D
Start-to-Finish with 5-day lag