← All PMI-RMP Flashcard Decks

The Risk Register Flashcards

7 cards from real PMI-RMP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 The Risk Register flashcards as text
  1. During which process is the risk register first created?

    Answer: Identify Risks

    The risk register is initially created as an output of the Identify Risks process.

  2. Which element is typically NOT recorded in the risk register at the moment of risk identification?

    Answer: Detailed quantitative cost impact in dollars

    Detailed quantitative cost impacts are added later during Perform Quantitative Risk Analysis, not at identification.

  3. What does the 'risk owner' field in the risk register designate?

    Answer: The person responsible for monitoring the risk and its response

    The risk owner is the person responsible for monitoring the risk and ensuring the response is carried out.

  4. After Plan Risk Responses, what new information is added to the risk register?

    Answer: Agreed-upon response strategies and response owners

    Plan Risk Responses adds chosen strategies, actions, response owners, and contingency plans to the register.

  5. How does the risk register differ from the risk report?

    Answer: The register lists individual risks; the report summarizes overall project risk and individual risk info

    The risk register details individual project risks, while the risk report presents sources of overall project risk plus summary information.

  6. A risk's status is updated to 'closed' in the register when:

    Answer: The risk can no longer occur or its trigger window has passed

    A risk is closed when it can no longer occur or has been fully resolved.

  7. Which document feeds risk-related lessons into organizational process assets at project close?

    Answer: The risk register and risk report

    Final versions of the risk register and risk report capture lessons learned for organizational process assets.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Exam format, retake policy, test dates, test delivery, renewal, score validity, exam information · verified Oct 2026