  1. What is the primary purpose of a Risk Breakdown Structure (RBS) in a project?

    Answer: To provide a hierarchical representation of risks organized by risk category

    The RBS provides a hierarchical decomposition of risks organized by category, helping teams systematically identify and organize project risks.

  2. Which of the following best describes the concept of risk categorization in project risk management?

    Answer: Grouping risks by their source, area of impact, or other useful classification

    Risk categorization involves grouping risks by characteristics such as their source, affected area, or phase to facilitate analysis and response planning.

  3. A project manager wants to ensure all sources of risk have been considered in a structured way. Which tool best supports this goal?

    Answer: Risk Breakdown Structure (RBS)

    The RBS organizes risks by source and category, helping teams systematically explore all potential risk sources and ensure comprehensive identification.

  4. Which of the following is typically a top-level category in a standard Risk Breakdown Structure?

    Answer: Technical risks

    Technical risks is a common top-level RBS category, alongside external, organizational, and project management risks, representing a major source of project uncertainty.

  5. What is a key benefit of using a hierarchical Risk Breakdown Structure during risk identification?

    Answer: It prompts team members to consider risks in every defined category systematically

    A hierarchical RBS serves as a prompt during brainstorming and workshops, ensuring the team considers risks across all defined categories systematically.

  6. Risk categories defined in the Risk Management Plan are used as an input to which risk identification technique?

    Answer: Prompt lists such as PESTLE or TECOP

    Prompt lists like PESTLE (Political, Economic, Social, Technological, Legal, Environmental) or TECOP align with RBS categories and use them as structured prompts for risk identification.

  7. When in the project risk management process is the Risk Breakdown Structure typically first developed?

    Answer: During Plan Risk Management, as part of defining the risk management approach

    The RBS is typically developed during Plan Risk Management as part of establishing the risk management approach, before risk identification begins.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Exam format, retake policy, test dates, test delivery, renewal, score validity, exam information · verified Oct 2026