Quantitative Risk Analysis Flashcards

7 cards from real PMI-RMP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Quantitative Risk Analysis flashcards as text
  1. In a Monte Carlo simulation of project cost, what does the P80 value on the cumulative S-curve represent?

    Answer: An 80% chance the actual cost will be at or below that value

    P80 means there is an 80% probability the outcome will be at or below that cost value.

  2. A risk has a 30% probability and would cost $50,000 if it occurs. What is its expected monetary value (EMV)?

    Answer: $15,000

    EMV equals probability times impact, so 0.30 × $50,000 = $15,000.

  3. Which distribution is most commonly used in three-point estimating with optimistic, most likely, and pessimistic values?

    Answer: Triangular or PERT (beta) distribution

    Three-point estimates feed triangular or PERT/beta distributions in quantitative analysis.

  4. In a decision tree, what does the EMV at a decision node typically guide the project manager to choose?

    Answer: The branch with the most favorable expected monetary value

    Decision-tree analysis selects the path with the best expected monetary value.

  5. A tornado diagram in quantitative risk analysis is primarily used to display what?

    Answer: The relative sensitivity of an outcome to individual risk variables

    Tornado diagrams rank variables by how strongly they influence the outcome, showing sensitivity.

  6. What is the main reason a project uses Monte Carlo simulation instead of a single deterministic estimate?

    Answer: It models combined uncertainty to produce a range of probable outcomes

    Monte Carlo captures combined uncertainty, yielding a probability distribution rather than one number.

  7. When running a schedule risk simulation, which network paths are most likely to become critical under uncertainty?

    Answer: Near-critical paths with high duration variability

    Near-critical paths with high variability can overtake the original critical path, revealing criticality risk.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Exam format, retake policy, test dates, test delivery, renewal, score validity, exam information · verified Oct 2026