Qualitative Risk Analysis Flashcards

7 cards from real PMI-RMP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Qualitative Risk Analysis flashcards as text
  1. A project manager assigns each identified risk a probability score of 1-5 and an impact score of 1-5, then multiplies them. What technique is being used?

    Answer: Probability and impact matrix

    Multiplying probability and impact scores to prioritize risks is the core of the probability and impact matrix used in qualitative analysis.

  2. During qualitative risk analysis, a risk's probability could not be reliably estimated because the data source was unverified. What should the team assess?

    Answer: The quality of the risk data

    Data quality assessment evaluates the accuracy and reliability of data used to analyze risks qualitatively.

  3. Which output is primarily updated as a result of performing qualitative risk analysis?

    Answer: Risk register

    Qualitative analysis updates the risk register with priority rankings, categorization, and watchlist items.

  4. A team groups risks by their root causes to determine which areas of the project are most exposed. What is this called?

    Answer: Risk categorization

    Risk categorization groups risks by sources, affected areas, or causes to reveal concentrations of exposure.

  5. Risks requiring near-term responses are flagged as more important during analysis. Which factor drives this prioritization?

    Answer: Risk urgency

    Risk urgency assessment prioritizes risks that need a response soon, often combined with the probability-impact rating.

  6. A stakeholder who is risk-averse rates the same impact level higher than a risk-tolerant stakeholder. What does this illustrate?

    Answer: The subjective bias inherent in qualitative analysis

    Qualitative analysis relies on subjective judgment, so perceptions and biases can influence ratings.

  7. After qualitative analysis, a low-priority risk is placed on a list for periodic monitoring with no immediate action. What is this list called?

    Answer: Watchlist

    Low-priority risks are added to a watchlist for ongoing monitoring rather than active response.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Exam format, retake policy, test dates, test delivery, renewal, score validity, exam information · verified Oct 2026