Opportunity Response Strategies Flashcards

7 cards from real PMI-RMP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Opportunity Response Strategies flashcards as text
  1. A project team identifies a chance to deliver early if a key vendor accelerates work, but the vendor's reliability is uncertain. The team partners with a specialized firm to jointly pursue the early-delivery upside. Which opportunity response strategy is this?

    Answer: Share

    Sharing transfers ownership of an opportunity to a third party best able to capture it, often via partnerships or joint ventures.

  2. Which opportunity response strategy seeks to ensure the opportunity definitely happens by removing all uncertainty about its occurrence?

    Answer: Exploit

    Exploit aims to make the opportunity's realization certain by eliminating the uncertainty of whether it occurs.

  3. A risk owner takes actions to increase the probability and positive impact of an opportunity without guaranteeing it. Which strategy is being applied?

    Answer: Enhance

    Enhance increases the likelihood or impact of an opportunity but does not make it certain.

  4. An opportunity falls outside the project manager's authority and would affect program-level objectives. The PM raises it to the program manager. This is which strategy?

    Answer: Escalate

    Escalation moves an opportunity to a higher level of authority when it is beyond the project's scope or the PM's authority.

  5. After analysis, a team decides to take no proactive action on a minor opportunity but will pursue it if it arises. This best illustrates which strategy?

    Answer: Accept

    Accept means taking no active steps to pursue the opportunity, acknowledging it without proactive measures.

  6. Which of the following is the BEST example of an exploit strategy for an opportunity?

    Answer: Assigning your most skilled resource to guarantee a task finishes ahead of schedule

    Assigning top talent to ensure the favorable outcome occurs is a classic exploit action that removes uncertainty.

  7. When an opportunity is escalated and accepted at the program level, who typically owns the response thereafter?

    Answer: The program or portfolio manager

    Once escalated and accepted, ownership transfers to the program or portfolio level and is no longer monitored by the project team.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Exam format, retake policy, test dates, test delivery, renewal, score validity, exam information · verified Oct 2026