PMI-PBA Certification Tasks & Techniques Flashcards
16 cards from real PMI PBA Certification practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 16 PMI-PBA Certification Tasks & Techniques flashcards as text
When two solution criteria are discovered to be in conflict, what should a business analyst do?
Answer: Communicate the conflict to stakeholders and facilitate a resolution.
When a business analyst discovers conflicting solution criteria, the most effective strategy is to communicate this conflict transparently to the relevant stakeholders. The business analyst's role then becomes to facilitate discussions and negotiations among these stakeholders to reach a mutually agreeable resolution. This ensures that decisions are made collaboratively and that the final solution aligns with the project's overall objectives.
A project to implement a new call management system for a help desk is being worked on by a business analyst. They anticipated that as time went on, the average response time would drop, but the opposite has happened. Which method should the business analyst employ to research the issue?
Answer: Root cause analysis
The problem describes an unexpected outcome where response times increased instead of decreasing, indicating a deviation from the anticipated behavior. Root cause analysis is a systematic process specifically designed to identify the underlying reasons or fundamental causes of a problem, rather than just addressing its symptoms. By employing this method, the business analyst can uncover why the new system is not performing as expected and address the core issue.
An additional demand was added to the scope of a project in the middle of it. The business analyst must ascertain whether the scope expansion has any implications, dependencies, or hazards. What action should the business analyst take to find these effects?
Answer: Manage solution scope
When an additional demand is added to the project scope, it constitutes a change to the solution being developed. The 'Manage solution scope' activity involves evaluating proposed changes to the solution, assessing their impact on existing requirements, design, and overall project objectives. This process helps the business analyst understand the implications, dependencies, and potential hazards of the scope expansion before it is approved and implemented.
After the product is baselined, the business analyst wants to make sure that requirement modifications can be properly monitored. What information will the business analyst require to assess the suggested change?
Answer: Impact analysis
After a product is baselined, any proposed modification needs a thorough assessment to understand its ramifications. Impact analysis is the process of evaluating the potential effects of a change on various aspects of the project, including existing requirements, design, schedule, cost, and resources. This information is crucial for the business analyst to present to stakeholders and the change control board, enabling informed decisions about whether to approve or reject the suggested change.
The business analyst is accountable for the following when a modification request is received:
Answer: analyzing the impact to the project schedule and budget.
Upon receiving a change request, the business analyst's primary responsibility is to analyze its potential effects across the project. This includes assessing how the change will impact the project's timeline (schedule) and financial resources (budget), as well as other factors like scope, quality, and resources. This comprehensive impact analysis provides the necessary data for the project manager and change control board to make an informed decision about approving or rejecting the change.
An experienced business analyst finds it challenging to choose between three alternative solution possibilities when creating a business case. An analysis supports a custom-developed solution, either domestically or utilizing contract labor, contrary to the senior vice president (SVP) who requested the business case's preference for an outsourced solution. How should the business analyst prepare the recommendation?
Answer: Formulate a weighted-ranking matrix
When faced with conflicting preferences and multiple solution options, a weighted-ranking matrix provides an objective and quantitative method for evaluation. This tool allows the business analyst to define various criteria (e.g., cost, risk, strategic alignment, stakeholder preference), assign weights to each criterion, and then score each solution option against these criteria. This approach helps to justify a recommendation based on data, even if it differs from a senior stakeholder's initial preference, fostering transparency and informed decision-making.
The finished product was supplied by the software engineers. The solution has been approved by the quality assurance team. What action is next for the business analyst?
Answer: Conduct user acceptance testing
After software engineers deliver the product and the quality assurance team has approved it, the next critical step is to ensure the solution meets the end-users' needs and business requirements. User Acceptance Testing (UAT) involves the actual end-users or client representatives testing the solution in a realistic environment. This process validates that the system functions as expected from a business perspective and is fit for purpose before final deployment.
The engineering, marketing, and human resources departments have all provided input on the business requirements for a new product. It would be better to: after examining the comments from the three departments.
Answer: collaborate on a product scope that aligns with the company’s objectives
When multiple departments provide input on business requirements, their individual needs may conflict or overlap. The most effective approach is to facilitate collaboration among these diverse stakeholders to define a unified product scope. This ensures that the final product aligns with the overarching company objectives, rather than just satisfying isolated departmental goals, leading to a more cohesive and strategically valuable solution.
The lead analyst position for a project is given to a business analyst. One of the biggest projects in the company's history, it has numerous components and intricate interfaces. A wide range of stakeholders will use the system that is currently being developed. Which tool ought the business analyst to employ to track the numerous requirements that this project will produce?
Answer: Sequence diagram
For a large project with numerous components, intricate interfaces, and a wide range of stakeholders, a robust system is needed to manage requirements effectively. A configuration management system is ideal for tracking requirements because it provides a structured approach to manage changes, maintain versions, establish baselines, and ensure traceability throughout the project lifecycle. While sequence diagrams model interactions, they are not designed for comprehensive requirement tracking and management.
The business analyst develops the specifications for a business analysis repository as a company uses SharePoint. The analyst outlines a thorough workflow in the requirements that includes email notifications being sent to the right parties for specific operations. The activities that should set off the notification procedure must be known to the SharePoint team. Which trigger for the workflow should the business analyst include?
Answer: Any change to the requirements matrix
The business analyst is designing a workflow for a business analysis repository that includes email notifications for specific operations. The requirements matrix (or traceability matrix) is the central repository for all project requirements, tracking their status, attributes, and relationships. Therefore, any change to this matrix—such as a new requirement, a modification, or a status update—is a critical event that should trigger notifications to relevant parties, ensuring everyone is kept informed of the latest requirement state.
Which of the following methods compares the present and ideal business perspectives to assess potential business changes?
Answer: SWOT analysis
Gap analysis is a technique used to compare the current state of a business process or system with its desired future state. It systematically identifies the 'gaps' or discrepancies between these two perspectives, highlighting what needs to be changed, developed, or improved to bridge the difference. This method is specifically designed to assess potential business changes by understanding what is missing or needs adjustment.
A stakeholder alerts the business analyst midway through the requirements gathering phase that a desired need does not address the solution. The interested party requests information about the requester. Hours are spent by the business analyst looking through emails to find the requestor. What needed to be documented by the business analyst?
Answer: Roles and responsibilities in the RACI matrix
The scenario describes the business analyst spending hours searching for the requester of a desired need. A requirements traceability matrix (RTM) is a crucial tool that links requirements to various attributes, including their source (who requested it), related design elements, test cases, and business objectives. Documenting the source in the RTM would have immediately provided the necessary information, preventing the time-consuming search and ensuring efficient requirement management.
How might a SWOT analysis be useful when selecting the best course of action to solve a company problem?
Answer: It can help the stakeholders identify the strengths and weaknesses of each option.
A SWOT analysis (Strengths, Weaknesses, Opportunities, Threats) is a strategic planning tool that helps evaluate an organization's internal capabilities and external factors. When applied to alternative solution options, it enables stakeholders to identify the inherent advantages (strengths) and disadvantages (weaknesses) of each choice. This comprehensive understanding is crucial for making an informed decision about the best course of action to address a company problem.
A customer modifies the business needs two weeks before delivery. What is the business analyst supposed to do?
Answer: Schedule a review by the change control board (CCB) to determine next steps.
Modifying business needs just two weeks before delivery is a significant change that impacts the project's baselined scope, schedule, and potentially cost. The business analyst must adhere to the established change control process, which typically involves submitting the change request to the Change Control Board (CCB). The CCB is responsible for reviewing, evaluating the impact of, and formally approving or rejecting such changes to maintain project integrity and control.
Which of the following criteria can be used to assess whether requirements match the goals of the product?
Answer: Business use cases
Business use cases describe how users interact with a system to achieve specific business goals, outlining the desired outcomes and interactions. By defining these high-level scenarios, business use cases provide a clear framework against which individual requirements can be assessed. This helps ensure that each requirement directly contributes to achieving the overall product goals and satisfies the intended user needs, verifying their alignment.
A feasibility study is being carried out by the business analyst to determine how well a proposed solution would work within the company. What kind of feasibility study is being conducted by the business analyst?
Answer: Operational
An operational feasibility study assesses how well a proposed solution will integrate and function within the organization's existing environment, processes, and culture. It considers whether the organization has the necessary resources, skills, and willingness to operate and maintain the new system effectively. The question specifically asks about how well the solution 'would work within the company,' which directly corresponds to the scope of operational feasibility.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pearsonvue.com — Test delivery · verified Oct 2026
- pmi.org — Exam format, renewal, time limit, score validity, passing score, retake policy, score release, test dates · verified Oct 2026