  1. Which method or instrument should be applied when evaluating the worth of a business case?

    Answer: Cost-benefit analysis

    To evaluate the worth of a business case, a cost-benefit analysis is the most appropriate method. This technique systematically compares the total costs of a project or initiative with its anticipated benefits. It helps determine if the financial and non-financial benefits outweigh the investment, providing a clear justification for proceeding or rejecting the business case.

  2. The deliverable of a project has been rejected by a stakeholder because it does not satisfy the initial business demand. Further analysis reveals that the deliverable does not satisfy the baseline's standards. What strategy will work the best to fix this problem?

    Answer: Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.

    If a deliverable meets the approved requirements baseline but a stakeholder rejects it based on a perceived unmet 'initial business demand' not in the baseline, the correct approach is to refer back to the agreed-upon baseline. The business analyst should provide the stakeholder with the approved documentation to clarify what was agreed upon. Any deviation from the baseline would require a formal change request process, not an immediate modification of the deliverable.

  3. The task of implementing a new phone system for a customer call center has been given to a business analyst. A business case will need to be made by the business analyst. Which of the aforementioned elements will the business analyst incorporate into the business case?

    Answer: Project scope

    A business case justifies the initiation of a project and typically includes a high-level overview of what the project aims to achieve. The project scope, which defines the work required to deliver a product, service, or result, is a fundamental element to include. It helps define the boundaries and objectives of the proposed initiative, providing clarity on what will be undertaken.

  4. Which method enables the collection of the most thoughts on a topic from a group without taking into account the truth or viability of the thoughts?

    Answer: Brainstorming

    Brainstorming is a technique specifically designed to generate a large number of ideas on a particular topic from a group. Its primary goal is to encourage creative thinking and quantity of ideas, often without immediate judgment of their truth or viability. This open approach helps uncover diverse perspectives and potential solutions.

  5. During the requirements collection stage of a project, the business analyst gets several revisions from various stakeholders. How should the business analyst keep track of the requirements throughout the project's lifespan to guarantee the delivery of the desired outcome?

    Answer: Perform inspections through the lifecycle of the project to detect any gaps and adjust the requirements baseline.

    To ensure the desired outcome despite multiple revisions, the business analyst must actively manage requirements throughout the project lifecycle. Performing regular inspections helps detect gaps, inconsistencies, or deviations from the intended solution. This proactive approach allows for timely adjustments to the requirements baseline, ensuring it remains accurate and aligned with project goals.

  6. Which project artifact is created or changed when a business analyst consults subject matter experts to specify roles and pinpoint influencers?

    Answer: Stakeholder register

    When a business analyst consults subject matter experts to specify roles and pinpoint influencers, they are gathering information critical for the stakeholder register. The stakeholder register is a project document that identifies all project stakeholders, along with their roles, interests, influence, and potential impact. This information is foundational for effective stakeholder management.

  7. Which of the following represents the ideal method for product validation?

    Answer: Two or more testers should test the product using the same test cases so that their evaluations are consistent.

    For ideal product validation, consistency and objectivity are key. Having two or more testers use the same test cases helps ensure that the product is evaluated against the same criteria and expected outcomes. This approach minimizes individual bias and increases the reliability and consistency of the validation results, confirming the product meets its requirements.

  8. The prospect of doing business abroad is being considered by an organization. Which elements ought to be looked into at the beginning of the initiative?

    Answer: Impacts on requirements baseline

    When an organization considers doing business abroad, it's crucial to investigate the impacts on the requirements baseline early in the initiative. International ventures introduce new considerations such as legal compliance, cultural differences, language variations, and local market needs, all of which can significantly alter or add to the initial requirements. Understanding these impacts upfront is vital for successful planning.

  9. What method or instrument is employed to secure acceptance of the given product?

    Answer: Inspection

    Inspection is a formal process of examining a work product or deliverable to determine if it meets specified requirements and standards. It is a critical method used to secure acceptance of a given product by verifying its quality and adherence to the agreed-upon baseline. This systematic review helps identify defects and ensures the product is fit for purpose.

  10. Which of the following instruments will aid in decision-making when stakeholders disagree on the merits of an initiative?

    Answer: Force-field analysis

    When stakeholders disagree on the merits of an initiative, a force-field analysis is an effective tool to aid decision-making. This technique helps visualize the driving forces (factors supporting the initiative) and restraining forces (factors opposing it). By identifying and weighing these forces, it provides a structured way to understand the dynamics of the disagreement and facilitate a resolution.

  11. A significant stakeholder is interested in how the addition of new features is developing as a product. What of the following has to be communicated to the stakeholder?

    Answer: Number of requirements tested and approved

    A significant stakeholder interested in the development progress of new features needs concrete metrics. Communicating the 'number of requirements tested and approved' provides a clear, measurable indicator of progress and quality. This metric directly reflects how many features have successfully gone through the validation process and are ready for deployment or have been deployed, offering tangible insight into product development.

  12. The person who is in charge of determining resource requirements and limits assists in carrying out business analysis operations.

    Answer: Project manager

    The project manager is typically responsible for determining resource requirements and constraints for the overall project, including those needed for business analysis activities. They manage the project budget, schedule, and resources, ensuring that the business analyst has the necessary support and limitations are understood. This role is crucial for enabling effective business analysis within project boundaries.

  13. When preparing business analysis, business analysts take into account each of the following factors. EXCEPT

    Answer: Development of project goals and objectives

    When preparing business analysis, a business analyst considers the project's context, characteristics, and stakeholder involvement, as well as the project lifecycle. However, the development of project goals and objectives typically occurs before or as part of the initial project definition phase, often driven by the business case or sponsor, rather than being developed during the BA planning phase itself.

  14. ______ are not taken into account in business analysis planning to guarantee that planning is done to a proper level.

    Answer: Project Sponsor

    Business analysis planning considers factors like project size, complexity, and the project manager's involvement to ensure the planning is appropriately scaled. The Project Sponsor, while a critical stakeholder who provides funding and high-level direction, is an input to the planning process rather than a factor that determines the *level* or *method* of planning itself.

  15. The method used to systematically collect and analyze qualitative and quantitative data to determine their interests as they relate to the entire project is called .

    Answer: Project analysis

    The description 'systematically collect and analyze qualitative and quantitative data to determine their interests as they relate to the entire project' most accurately describes Project Analysis in a broad sense. This encompasses various analytical activities, including stakeholder analysis, to understand the overall project landscape, its components, and the interests of various groups involved.

  16. To evaluate the stakeholder groups that affect and have an impact on the project activity, ______ uses stakeholder analysis.

    Answer: Project manager

    The project manager uses stakeholder analysis to evaluate the various stakeholder groups that affect and are affected by the project activities. This analysis helps the project manager understand stakeholder influence, interests, and potential impact. This understanding is crucial for developing effective stakeholder engagement strategies and ensuring project success.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Exam format, renewal, time limit, score validity, passing score, retake policy, score release, test dates, exam information · verified Oct 2026
  2. pearsonvue.com — Test delivery · verified Oct 2026