- What method or instrument is employed to secure acceptance of the given product? → Inspection
- When eliciting requirements for a legacy system replacement, which technique is MOST valuable for understanding current state processes? → Observation (job shadowing)
- A stakeholder signs off on requirements but later claims the delivered solution does not meet their needs. Which BA practice BEST prevents this situation? → Using prototypes or models to confirm shared understanding before sign-off
- Which type of requirement describes the quality attributes a system must meet, such as performance or security? → Non-functional requirement
- There are linked attributes that are developed and used to monitor and regulate product scope. → Traceability matrix
- Business analysis is a process used to evaluate the existing internal and external environment and analyze a current business opportunity or problem. → Need Assessment
- Which PMI-PBA knowledge area focuses on understanding stakeholder needs and translating them into actionable requirements? → Requirements Analysis and Design Definition
- One of the main difficulties in eliciting requirements is . → Recording the voice of the costumer
- Which document formally authorizes a business analyst to begin work on a project? → Project Charter
- Where else would you utilize decision trees if not for developing business rules? → Quantitative risk assessment
- ______ are not taken into account in business analysis planning to guarantee that planning is done to a proper level. → Project Sponsor
- Determine the methods for mass elicitation used in business planning → All the above
- Which stakeholder analysis technique creates a visual representation of stakeholders based on their level of power and interest in the project? → Power/interest grid
- Which elicitation technique is BEST suited for eliciting requirements from a large group of stakeholders with diverse opinions quickly? → Surveys and questionnaires
- Which requirements attribute helps a BA determine whether a requirement can be tested to confirm it has been met? → Verifiability
- A project is in the middle of execution and a stakeholder requests a significant scope change. According to PMI-PBA practices, what should the BA do FIRST? → Assess the impact of the change on existing requirements and project objectives
- Conflict resolution, planning for incremental deliverables, preventing scope creep, and making necessary decisions are all made easier with the _____ technique. → Prioritization
- Which requirements classification describes a requirement that defines how the system must interact with other external systems? → Interface requirements
- Which of the following instruments will aid in decision-making when stakeholders disagree on the merits of an initiative? → Force-field analysis
- When managing requirements for an agile project, how are requirements typically captured? → As user stories in a product backlog, refined iteratively
- Which elicitation technique is MOST effective when stakeholders are geographically dispersed and time zones prevent synchronous meetings? → Surveys and questionnaires
- When adjusting expectations for the future, ______ are used to assess the performance in comparison to what was anticipated to be accomplished. → Preparation notes
- During requirements elicitation, a BA notices that two stakeholders give conflicting information about a process. What should the BA do first? → Facilitate a joint session to surface and resolve the conflict collaboratively
- User story definition and ______ in requirement analysis support one another → Acceptance criteria
- In a PMI-PBA context, what is the PRIMARY purpose of a Business Analysis Plan (BAP)? → To define how business analysis activities will be performed, monitored, and controlled
- A stakeholder says 'the system must be user-friendly.' How should a BA handle this requirement? → Probe further to define measurable criteria that define 'user-friendly'
- According to the PMI Guide to Business Analysis, which of the following is an INPUT to the Plan Business Analysis Approach task? → Organizational process assets
- A business analyst is performing a traceability audit and finds several requirements with no associated test cases. What is the risk? → Those requirements may not be tested, leading to undetected gaps in the delivered solution
- Which technique is BEST suited for validating that a solution meets user needs by having actual users interact with it? → User acceptance testing (UAT)
- When two solution criteria are discovered to be in conflict, what should a business analyst do? → Communicate the conflict to stakeholders and facilitate a resolution.