A program sponsor requests accelerating the timeline by six months to capture a market opportunity. The program manager should FIRST:
-
A
Immediately compress all project schedules
-
B
Perform an impact analysis on scope, cost, quality, and risk before committing
-
C
Decline the request since the original plan was approved
-
D
Ask the PMO to approve the change without analysis