A program manager discovers that two component projects share a critical resource, creating a scheduling conflict. What is the BEST first action?
-
A
Escalate to the sponsor immediately
-
B
Analyze the dependency and negotiate a resource-sharing agreement between project managers
-
C
Cancel the lower-priority project
-
D
Request additional budget to hire duplicate resources