A program manager notices that a project's Schedule Performance Index (SPI) is 0.85. What does this indicate?
-
A
The project is 15% ahead of schedule
-
B
The project is performing at 85% of the planned schedule efficiency
-
C
The project has spent 85% of its budget
-
D
The project quality score is 85%