A program manager discovers that two project teams have conflicting priorities causing schedule slippage. What is the MOST effective first step?
-
A
Escalate immediately to the program sponsor
-
B
Facilitate a joint meeting to surface underlying interests and negotiate a shared resolution
-
C
Reassign resources from one team to the other
-
D
Document the conflict and wait for teams to self-resolve