A mechanical engineer requests a PCB outline change after the layout is 80% complete. What is the best first step?
-
A
Reject the request to protect schedule
-
B
Assess the impact on component placement and routing before responding
-
C
Immediately update the board outline
-
D
Escalate to the project manager without analysis