A Scrum Team consistently fails to meet its Sprint Goal because of dependencies on another team that is not using Scrum and frequently delivers their part late. What is the most effective leadership action for the Scrum Master to take?
-
A
Tell the Developers to work harder to overcome the dependency.
-
B
Facilitate a meeting between the two teams to create a shared understanding and a working agreement.
-
C
Escalate the issue to senior management and ask them to force the other team to deliver on time.
-
D
Advise the Product Owner to plan for less work in future Sprints to account for the delays.