A Scrum Team notices that their Sprint Goal becomes irrelevant halfway through the Sprint due to a market shift. What should happen?
-
A
The Sprint should be cancelled by the Product Owner
-
B
The team must complete the Sprint as planned
-
C
The Scrum Master cancels the Sprint unilaterally
-
D
The Development Team votes on whether to continue