A Product Owner is asked by key stakeholders for a specific date when a large set of features will be delivered. The Scrum Team has been working for several Sprints and has a relatively stable velocity. What is the most agile and transparent way for the Product Owner to respond?
-
A
Commit to the date requested by the stakeholders and push the Developers to increase their velocity to meet it.
-
B
Provide a forecast using a range of dates based on optimistic and pessimistic scenarios of the team's velocity and the likely scope.
-
C
Explain that forecasting is impossible in Scrum and refuse to provide any date range.
-
D
Give a single, fixed date based on the current average velocity to provide a clear target.