A project manager is analyzing the project schedule and identifies a series of activities with zero total float. Any delay to one of these activities will cause a delay to the project completion date. What does this series of activities represent?
-
A
The critical path
-
B
A near-critical path
-
C
The baseline schedule
-
D
A schedule buffer