A project manager is assigned to a new strategic initiative. During initial meetings, they discover that key stakeholders have conflicting understandings of the project's objectives, success criteria, and high-level deliverables. A formal project charter has not been created. What is the project manager's BEST course of action?
-
A
Begin creating a detailed Work Breakdown Structure (WBS) with the project team.
-
B
Facilitate the development and approval of a project charter with the sponsor and key stakeholders.
-
C
Proceed with project planning based on their own interpretation of the stakeholder discussions.
-
D
Schedule a project kickoff meeting to vote on the primary objectives.