A project manager observes that the project team, which has been working together for several weeks, is experiencing frequent disagreements and challenges to the project manager's authority. Despite the conflicts, team members are beginning to express their true opinions. According to the Tuckman ladder model, which stage of team development is the team most likely in?
-
A
Norming
-
B
Storming
-
C
Forming
-
D
Performing