A project has a Cost Performance Index (CPI) of 0.85 and a Schedule Performance Index (SPI) of 1.05. Based on these metrics, what is the current status of the project?
-
A
The project is over budget and ahead of schedule.
-
B
The project is under budget and behind schedule.
-
C
The project is over budget and behind schedule.
-
D
The project is under budget and ahead of schedule.