According to Massachusetts Dig Safe law (M.G.L. c. 82, § 40A), what is the minimum required notice an excavator must provide to the Dig Safe system before starting a non-emergency excavation?
-
A
48 hours, including weekends and holidays
-
B
At least 24 hours, but not more than 30 days
-
C
72 hours, excluding Saturdays, Sundays, and legal holidays
-
D
One full business week (5 business days)