A fabricator has a WPS qualified for a groove weld on 1-inch thick carbon steel plate. The WPS specifies a 1/8" E7018 electrode. An engineer wants to use a 5/32" E7018 electrode for increased deposition rate, which is a change in an essential variable according to ASME IX. What must be done before this change can be implemented in production?
-
A
Revise the WPS to reflect the new electrode size and proceed with production.
-
B
Perform a new Welder Performance Qualification Test (WPQ) with the 5/32" electrode.
-
C
Weld a new test coupon using the 5/32" electrode, perform the required testing, and document the results on a new PQR.
-
D
Submit a formal request to the client to waive the requalification requirement.