During a monthly site observation visit, the landscape architect notices that the contractor has installed site furnishings that do not match the approved submittals. What is the landscape architect's most appropriate initial action?
-
A
Issue a stop-work order for the entire project.
-
B
Document the non-conforming work in a field report and formally notify the contractor in writing.
-
C
Verbally instruct the contractor's crew to immediately remove the incorrect furnishings.
-
D
Prepare a change order to accept the non-conforming work.