What is the primary purpose of construction management in landscape architecture?
Correct!
Wrong!
Construction management ensures that all phases of construction adhere to the predetermined budget, timeline, and design specifications.
What document outlines the scope of work, project details, and responsibilities during construction?
Correct!
Wrong!
A construction contract defines the terms and expectations for all parties involved in the project.
During a site inspection, the landscape architect discovers a safety hazard. What should be their first step?
Correct!
Wrong!
Immediate documentation and communication with the contractor ensure safety issues are resolved promptly.
What is a "change order" in construction management?
Correct!
Wrong!
Change orders formalize any adjustments to the original project plan and require approval from all relevant parties.
What tool is most commonly used to monitor the project timeline in construction management?
Correct!
Wrong!
Gantt charts provide a visual representation of project tasks, deadlines, and dependencies, facilitating schedule tracking.