During the bidding phase for a public park project, a landscape architect issues an addendum.
What is the primary purpose of this document?
Select your answer
A
To negotiate the final contract price with the selected bidder.
B
To formally award the construction contract to the lowest responsible bidder.
C
To modify or clarify the bidding documents before the bid submission deadline.
D
To approve a contractor's substitution request after the contract has been signed.