A hospital is implementing a new enterprise-wide PACS. During the project, the radiology department requests the addition of an advanced 3D visualization module that was not included in the original project scope. This is an example of:
-
A
Scope creep
-
B
Risk mitigation
-
C
Stakeholder analysis
-
D
Project charter finalization