Under OSHA 1926.1412, what must a crane operator do before beginning any lifting operations?
-
A
Conduct a pre-shift visual inspection of the crane, including controls, safety devices, wire rope, and operational aids
-
B
Review only the manufacturer's load chart for the day's lifts
-
C
Obtain verbal approval from the site superintendent
-
D
Test the load by lifting it 1 inch off the ground for 30 seconds