Which of the following is the primary accountability of the Product Owner?
-
A
Managing the project budget and timeline.
-
B
Maximizing the value of the product resulting from the work of the Scrum Team.
-
C
Facilitating all Scrum events and ensuring they are productive.
-
D
Directing the daily tasks of the Developers.