A team is reviewing their Cumulative Flow Diagram (CFD).
They notice that the band representing the 'In Progress' stage is consistently widening over time, while the 'Done' band is flattening.
What is the most likely interpretation of this pattern?
Select your answer
A
The team's Work in Progress (WIP) limits are too low, starving the team of work.
B
The project scope is decreasing as features are being completed and removed.
C
A bottleneck exists where work is entering the 'In Progress' stage faster than it is leaving.
D
The team is becoming more efficient and finishing work faster than new work is starting.