During a Sprint Review, the Scrum Team presents the work completed in the Sprint. Key stakeholders are present and provide feedback. What is the primary purpose of this event?
-
A
To provide a status update and get formal sign-off on the Increment.
-
B
To inspect the outcome of the Sprint and determine future adaptations to the Product Backlog.
-
C
To hold a demonstration of the new features for the management team.
-
D
To assess the team's velocity and plan the capacity for the next Sprint.