An Agile Coach is reviewing a team's Cumulative Flow Diagram (CFD). They notice that over the last several weeks, the band representing the 'Testing' phase is progressively widening, while the 'Done' band's slope is much flatter by comparison. What is the most likely conclusion?
-
A
The team's overall velocity is increasing steadily.
-
B
Work is entering the testing phase faster than it is being completed, indicating a bottleneck.
-
C
The Product Owner is adding new work to the sprint at an unsustainable rate.
-
D
The development team is completing their work ahead of schedule.