A project manager discovers that two key stakeholders have conflicting expectations about deliverable timelines. What is the BEST first step?
-
A
Proceed with the timeline preferred by the higher-ranking stakeholder
-
B
Facilitate a joint meeting to surface and reconcile the conflicting expectations
-
C
Send separate emails to each stakeholder explaining the other's position
-
D
Escalate the conflict to executive leadership immediately