A project manager notices that actual costs have exceeded the planned budget at the midpoint of a project. Which Earned Value metric best quantifies this variance?
-
A
Schedule Variance (SV)
-
B
Cost Variance (CV)
-
C
Cost Performance Index (CPI)
-
D
Budget at Completion (BAC)