Under CDM 2015, when must a project be notified to the HSE?
-
A
When the construction phase will last longer than 30 working days with more than 20 workers simultaneously, or exceed 500 person-days
-
B
When the project costs more than ยฃ500,000
-
C
When more than 10 contractors are involved
-
D
When the project involves working at height