Under the Construction (Design and Management) Regulations 2015 (CDM 2015), who has the duty to appoint a principal designer and principal contractor on projects involving more than one contractor?
-
A
The client
-
B
The principal contractor
-
C
The Health and Safety Executive
-
D
The local authority