A client requests a 'load-bearing' interior wall be removed to open up a floor plan. What is the designer's FIRST responsibility?
-
A
Hire a contractor to remove the wall immediately
-
B
Specify new finishes for the enlarged space
-
C
Recommend consulting a structural engineer before any demolition
-
D
Apply for a building permit without further investigation