  1. According to the NEC, what is the minimum size conductor permitted for a 200-amp residential service entrance?

    Answer: 3/0 AWG copper

    Per NEC Table 310.12, a 200-amp service requires a minimum of 3/0 AWG copper or 4/0 AWG aluminum conductors.

  2. What is the maximum number of overcurrent devices permitted on a single panelboard in accordance with NEC Article 408?

    Answer: 42

    NEC 408.54 limits a panelboard to a maximum of 42 overcurrent devices (excluding the main breaker).

  3. When calculating feeder demand load for a commercial kitchen, what demand factor applies to the first 12 kW of commercial electric cooking equipment per NEC Table 220.56?

    Answer: 65%

    NEC Table 220.56 permits a 65% demand factor for commercial electric cooking equipment rated over 12 kW.

  4. A multiwire branch circuit supplying line-to-neutral loads must be disconnected simultaneously by which means?

    Answer: A multipole breaker or handle ties

    NEC 210.4(B) requires multiwire branch circuits to be disconnected simultaneously using multipole breakers or approved handle ties.

  5. What is the maximum continuous load permitted on a branch circuit breaker rated at 30 amperes?

    Answer: 24 amperes

    Continuous loads are limited to 80% of the overcurrent device rating, so 30A × 0.80 = 24 amperes.

  6. Per NEC 215.2(A)(1), feeder conductors must have an ampacity not less than required to supply the load as calculated in which parts of Article 220?

    Answer: Parts I through V

    NEC 215.2(A)(1) requires feeder conductors to have ampacity sufficient for loads calculated per Parts I through V of Article 220.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. cslb.ca.gov — Eligibility, fees, renewal · verified Nov 2026
  2. www2.myfloridalicense.com — Exam format, passing score, retake policy, score release, time limit, test delivery, test dates · verified Nov 2026
  3. ncbeec.org — Test delivery, fees, exam format, passing score, retake policy, score release, test dates, time limit · verified Nov 2026
FREE Licensed Electrical Contractor Services, Feeders, and Branch Circuits Questions and Answers Flashcards — Licensed Electrical Contractor Study Cards with Answers