According to OSHA 29 CFR 1926, what is the minimum clearance distance a worker must maintain from an unguarded energized overhead power line operating at 50 kV or less?
Answer: 10 feet
OSHA 29 CFR 1926.416 and NFPA 70E require a minimum 10-foot clearance from unguarded energized overhead lines rated up to 50 kV.
A change order on a construction project is best described as:
Answer: A written amendment modifying the original contract scope, cost, or schedule
A change order is a formal written document that modifies the original contract terms, including changes to scope of work, price, or completion date.
Under NFPA 70E, an arc flash hazard analysis must be performed to establish:
Answer: Incident energy levels and appropriate PPE boundaries
An arc flash hazard analysis determines the incident energy at a work location and the required PPE, as well as flash protection and limited approach boundaries.
Which IRS form is used to report payments of $600 or more to a subcontractor who is not incorporated?
Answer: 1099-NEC
Contractors must issue Form 1099-NEC (Non-Employee Compensation) to unincorporated subcontractors paid $600 or more during a tax year.
What is the primary purpose of a mechanics' lien in the construction industry?
Answer: To secure payment for labor or materials provided to a property
A mechanics' lien is a legal claim against a property that helps ensure subcontractors and suppliers can collect payment for work or materials provided.
Under the NEC, the grounding electrode system for a building must include which of the following if present on the property?
Answer: A metal underground water pipe in contact with earth for 10 feet or more
NEC 250.52(A)(1) requires that a metal underground water pipe with at least 10 feet of contact with the earth be used as a grounding electrode.
An electrical contractor purchases a commercial general liability (CGL) policy. This policy primarily protects against:
Answer: Bodily injury and property damage claims from third parties
A CGL policy covers third-party claims for bodily injury and property damage arising from the contractor's operations or completed work.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- cslb.ca.gov — Eligibility, fees, renewal · verified Nov 2026
- www2.myfloridalicense.com — Exam format, passing score, retake policy, score release, time limit, test delivery, test dates · verified Nov 2026
- ncbeec.org — Test delivery, fees, exam format, passing score, retake policy, score release, test dates, time limit · verified Nov 2026