Which statement best explains why baselining current process performance is important in the Define phase?
-
A
It provides a reference point to measure improvement after changes are implemented
-
B
It allows the team to immediately identify root causes
-
C
It replaces the need for a project charter
-
D
It eliminates the need for stakeholder buy-in