What is the primary purpose of a Control Plan in the Control phase of DMAIC?
Select your answer
A
To document the project timeline and team responsibilities
B
To specify what process variables to monitor, how to measure them, the sampling frequency, and the response if limits are exceeded
C
To summarize the financial savings achieved by the project
D
To replace the project charter once improvements are implemented