What is the purpose of a 'handoff' or transition plan at the end of a DMAIC project?
-
A
To transfer project documentation to the finance department for cost tracking
-
B
To ensure the process owner and operators can sustain the improvements without the project team
-
C
To formally close the project charter and release team members
-
D
To schedule a follow-up DMAIC project on the same process