What is the main purpose of a 'transition plan' at the end of a Lean Six Sigma project?
-
A
To document lessons learned for the project portfolio
-
B
To hand off ownership of the improved process and controls to the process owner
-
C
To identify the next improvement project
-
D
To calculate final project savings