A team calculates Pp = 1.45 and Ppk = 0.92 for a new process. What is the most likely explanation?
-
A
The process is centered and capable
-
B
The process has adequate spread but is significantly off-center
-
C
The process has too much variation to be useful
-
D
Pp and Ppk cannot differ by this amount