A team finds that its process average has shifted by 1.5 sigma over time. According to Lean Six Sigma convention, how does this assumption affect the reported DPMO for a Six Sigma process?
-
A
DPMO increases from 3.4 to 233
-
B
DPMO increases from near zero to 3.4
-
C
DPMO decreases because the shift is accounted for in Ppk
-
D
DPMO is unaffected because it is based on Cpk, not the mean