What is the MAIN risk of setting control limits too wide on an X-bar chart?
-
A
The chart will generate too many false alarms
-
B
Real process shifts may not be detected until many defects are produced
-
C
Operators will adjust the process too frequently
-
D
The subgroup sample size will need to increase