An assembly line worker must stop production for 20 minutes each shift while waiting for a parts delivery from an upstream supplier. Which of the 8 Lean wastes does this scenario most directly illustrate?
-
A
Transportation
-
B
Inventory
-
C
Waiting
-
D
Motion