Which of the following is an example of a well-written project charter problem statement?
-
A
Customer complaints are caused by inadequate training of service reps.
-
B
Reduce defect rate by 50% within six months.
-
C
Order processing errors average 12% over the last quarter, resulting in $2M in rework costs annually.
-
D
The order processing system needs to be replaced with a new ERP platform.