A team is assessing a transactional process and wants to quantify how much time is spent on value-added versus non-value-added activities. Which metric is most appropriate?
-
A
Process cycle efficiency (PCE)
-
B
Takt time
-
C
Defects per unit (DPU)
-
D
Overall equipment effectiveness (OEE)