Which strategy is most effective for managing stakeholder expectations during a facility renovation project?
-
A
Avoiding all communication until the project is complete
-
B
Providing regular progress updates and addressing concerns proactively
-
C
Only communicating through formal written notices
-
D
Delegating all communication to the contractor